Download Presentation The PPT/PDF document "ELCITA Update May 2016 4" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
ELCITA Update
May 2016
Slide24
Estate Management
Skywalk
M/s
mayaPRAXIS
had submitted the draft preliminary feasibility study Report on Skywalk system for Electronics city phase 1.
E
– Toilets
15 e-toilets operational, e-toilets installation work in progress.
Estate survey
Roads & common area survey completed for Phase 1& 2. Plot Inventory of the
Industries -
completed
.
Soft copy of base map drawing of Phase 1 has been submitted for ELCITA
review - Completed.
GIS Web Application Software
work verification
in progress.
Slide33
Estate Management
Permanent Works - Under Progress
WIPRO
Neeladri
Road
Cdot
Dmart
Road
Slide44
Estate Management
Maintenance – Under Progress
Drain work At KSSIDC Complex
Laying Pavers in Front of Lemon Tree Hotel
Slide55
Estate Management
Drai
n work in Canara Bank/ Fire station junction
Maintenance – Under progress
Shoulder Drain work at Various location
Slide66
Estate Management
Maintenance – Under progress
Construction of Drain, Cover slabs along HP Avenue Road
Laying Pavers Along HP Avenue Road
Slide77
Estate Management
Maintenance –
Completed
Drain work
Along
Gollahalli
Road
Cover Slab work at BESCOM
Slide88
Estate Management
Maintenance – Under progress
Re Fixing of
Kerbstone
and providing pavers along
Velankani
Road
Re fixing Drain cover slab in front of Lord Plaza
Slide99
Estate Management
RMU yard at Wipro Gate no 5
Maintenance –
Completed
Drain Cleaning Work
Slide1010
Estate Management
Maintenance –
Completed
Drain work adjacent to
RajKamal
Industries
Cross Drainage work at
Gollahalli
Junction
Slide1111
Estate Management
Drai
n work in front of BETL
Maintenance –
Completed
Footpath work in front of KFC
Slide1212
Estate Management
Maintenance –
Completed
Providing & Laying Sewer line, Electronics City Phase 2
Construction of Drain from JJ
glastronics
to existing drain
Slide1313
Estate Management
Supply & Erection of Shed for Organic waste processing
plant & Shredding Area
at KIADB Land –
Ecity
Phase 2
Sustainability Works – Completed
Slide1414
Estate Management
Maintenance –
Completed
Construction of Compound Wall at Wipro Gate No 5
Construction of Compound Wall at Wipro Gate No 12 A
Slide1515
Estate Management
Maintenance –
Under Progress
WMM Road from MSME Building to Exit Gate
Drain from 300KLD STP to Outside
Slide1616
Estate Management
Road Works - Under Progress
WIPRO
Neeladri
Road
Doddanagamangala
Village Concrete Road
Slide1717
Estate Management
Road Works
– Under Progress
HP Avenue
Road
Canara Bank to
Firestation
Road
Slide1818
Estate Management
Road Works -
Completed
Quasitum
Road
Bhavani
Industries Road
Slide1919
Estate Management
RWH works – Under Progress
SI.NO
DESCRIPTION
N
O OF PITS
STATUS
1
RAIN WATER
HATVESTINH PIT
38COMPLETED
2
RAIN WATER HATVESTINH PIT12TO BE AWARDED
Slide2020
Estate Management
Contract Awarded
Providing and laying of Asphalting using 60/70 grade bitumen along
Café
Corner & JP IT Park Road
C-DOT to D-Mart Road Junction
21
Estate Management
Contracts on Anvil
Construction
of Drains, laying of Pavers,
Kerb
stones and Drain cover slabs along
TCS Road
Providing UGD
to connect industries in cluster 2 & 3 to the 300 KLD
STP.
Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2