/
Fire  Safety update Mike Kay, CEO Fire  Safety update Mike Kay, CEO

Fire Safety update Mike Kay, CEO - PowerPoint Presentation

myesha-ticknor
myesha-ticknor . @myesha-ticknor
Follow
349 views
Uploaded On 2018-11-06

Fire Safety update Mike Kay, CEO - PPT Presentation

amp Michael Lyons Interim Compliance Manager 4 th July 2017 CURRENT POSITION NPH Liaison and agreement with NFRS Northampton Fire and Rescue Service and NBC NFRS do 3 things 1 Enforcement Inspections ID: 717235

safety fire risk blocks fire safety blocks risk nph high nbc stay fra put current 100 external cladding katherines court ewi tower

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Fire Safety update Mike Kay, CEO" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Fire Safety update

Mike Kay, CEO&Michael Lyons, Interim Compliance Manager

4

th

July 2017Slide2

CURRENT POSITIONNPH Liaison and agreement with NFRS (Northampton Fire and Rescue Service) and NBCNFRS do 3 things:1. Enforcement Inspections

2. Building Information for Fire Fighting3. Home Fire Safety ChecksNFRS Objective is PREVENTIONThey do not issue fire certificates, approve installations, give instructions etcSlide3

CURRENT POSITIONHeadlinesNPH work to and comply with The Regulatory Reform (Fire Safety) Order 2005“Responsible Person” – NPH“Suitable and sufficient Risk Assessment”

Includes adequate fire safety arrangements including evacuation strategies“Stay Put” StrategyNFRS evacuate if requiredEffective compartmentation and suitably protected means of escapeSprinklers are not recommended “Zero Tolerance” approach to fire escape routesSlide4

Fire Safety updateMichael Lyons

Interim Compliance Manager Slide5

Overview on NPH Fire arrangementsFollowing the tragic incident at Grenfell Tower in London, NPH has carried out extra safety checks in all the blocks that we manage on behalf of NBC. We have focused on a portfolio of blocks that are 18 metres

and above, a rule used by the government and fire service.The events at Grenfell Tower have raised questions from the public about how social landlords and their managing agents ensure the safety of their tenants and the blocks they live in. This presentation offers an overview on fire safety within the properties managed by NPH including:Cladding and External Wall Insulation (EWI)The stay put arrangement

Current fire safety arrangements

A

ctivities since the London fireSlide6

Cladding & EWISpeculation has raised questions over the use of External Cladding and EWI –in particular (ACM’s) Aluminium Composite M

aterial.In regards to NBC blocks:Cladding on St Katherines Court is a different material to the one used on Grenfell Tower. It is a layered composite zero fire rated material. This rating is awarded to the highest fire retardant building materials such as concrete, steel and brick.

The insulation used on St Katherines Court is a mineral wool, which is also fire retardant and does not support combustion.

The methods of installation used on St Katherines Court, and on all NBC properties where EWI has been installed have additional fire breaks built into the design.

T

hese fire breaks offer additional compartmentalisation vertically and horizontally.

EWI is a method used to provide thermal insulation to the outside of a building. The fire protection element of EWI comes from the stringent instillation methods used, and the addition of layers of silicon and then an external render that are placed over the insulation material.Slide7

The Stay Put Arrangement

The stay put arrangement is a nationally recognised approach used by social and private landlords to manage the safety of residents in blocks. NPH would only review its approach to the stay put arrangements if it was advised to do so by Fire Services nationally. Over the past 2 years NPH has invested significantly into fire safety, as well as working closely with partners to ensure the highest levels of fire safety for NBC tenants. Slide8

The Stay Put ArrangementThe following arrangements are in place and contribute to NPH offering assurance on fire to its tenants, board and NBC

:Over 4,000 fire doors replaced All 670 properties requiring an Fire Risk Assessment (FRA) have a full and valid FRANPH has a dedicated in-house Fire Safety OfficerAll works stemming from an FRA are managed by the Fire safety OfficerFire safety is a priority on all Planned Investment and regeneration works undertaken by the Asset

team

The estate teams and housing officers undertake regular inspections on all sites regularly

The fire service have attended multiple blocks over the past 2 weeks and are satisfied with the stay put arrangement employed by NPHSlide9

Current fire safety arrangements on tower blocksNPH manages circa 11,700 properties on behalf of Northampton Borough Council. The portfolio includes 670 locations that require an FRA, of those 670 only 11 are above

5 storeys, and only one block (St Katherines Court) could be categorised as approaching high-rise. All blocks are fully compliantSlide10

Current fire safety arrangementsUnder the Regulatory Reform Fire Safety Order (2005), NPH is fully compliant and has completed its duty to carry out FRA’s on all locations where they are required. These FRAs are programmed in on a rolling basis, and ensures all locations are assessed on a frequency relative to the risk associated with a block. The current inspection regime and compliance data is outlined below:

NPH has reviewed all high risk FRA’s and revised FRA’s are now in place on all these assets.

Risk rating

Risk Criteria

Number of blocks

FRA schedule

FRA compliance

High Risk

5 storeys or higher

11 Blocks

Annual

100%

High Risk

Sheltered Blocks

1 Block

Eleonore House

Annual

100%

High Risk

Community Hubs

18

Annual

100%

Medium

Under 5 floors with 20 + flats

15 Blocks

Annual

100%

Medium

Blocks with 7-12 flats

524 Blocks

2 years

100%

Low Risk

Blocks with 1-6 flats

101 Blocks

3 years

100%Slide11

Activities since the London fireSince Grenfell Tower, NPH has carried out additional validation works on all blocks. Initially these activities focused

on the 11 blocks managed by NPH that are above 5 storeys. The scope of this project expanded to include input and requirements from external partners including the Fire Service, central government (DCLG and HCA) and local government. Slide12

Activities since the London fireThe previously mentioned revision of all high risk FRA’s was instructed commencing with the 11 high risk blocksAll fire alarms and detection systems were testedAll

emergency lighting has been re-tested in all 11 high risk blocksAn external review of cladding from St Katherines Court was instructedAn external review of the NPH FRA programme has been agreed and is being instructed w/e 14th July when a contractor is agreedNPH’s fire officer has conducted

6

joint

visits on NBC blocks, and a further 9 others are planned

The

Department for Communities and Local Government (DCLG) request

information

sheets were completed for all blocks above 6

stories

A Fire Safety update was provided to NBC for the full

Council meeting on

Monday 19th

June

A report was delivered to

NPH’s Audit

& Risk Committee on 27

th

June, the committee noted they received assurance from the reportSlide13

Thanks you for your attentionAny Questions?