Lafayette  New Terminal Program Update Lafayette  New Terminal Program Update

Lafayette New Terminal Program Update - PowerPoint Presentation

pamella-moone
pamella-moone . @pamella-moone
Follow
353 views
Uploaded On 2018-09-16

Lafayette New Terminal Program Update - PPT Presentation

April 11 2018 1 Agenda Airside and Landside Site Analysis Terminal Facility Cost Schedule CMAR Coordination Next 60 days 2 Overall Site Plan April 2018 3 QTA 4 Meeting with Rental Car Agencies to review design scheduled for May 3 2018 ID: 667678

terminal 2018 design april 2018 terminal april design cable qta estimate layout floor mar schedule cmar rtr civil reconciliation dec facility temporary

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Lafayette New Terminal Program Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Lafayette

New Terminal Program Update

April 11, 2018

1Slide2

Agenda

Airside and Landside Site Analysis Terminal FacilityCost Schedule CMAR CoordinationNext 60 days

2Slide3

Overall Site Plan – April 2018

3Slide4

QTA

4

Meeting with Rental Car Agencies to review design scheduled for May 3, 2018Slide5

QTA

5Slide6

Temporary RTR Cable

6

October 2017 Temporary Cable

April 2018 Temporary Cable Slide7

Proposed RTR Facility

7

Proposed RTR Facility

Taxiway M

ARFF

Bell

HelicopterSlide8

1st Floor Layout – April 2018

8Slide9

1st Floor Layout – April 2018

9Slide10

2nd Floor Layout – April 2018

10Slide11

2nd Floor Layout – April 2018

11

Concessions, SARA, Mother’s Room

TSA, Security, LAC Office and Commission RoomsSlide12

BudgetTerminal Program Budget

Current Estimate 12Slide13

Estimate

13Completed 30% design estimate reconciliation with the CMARDifference is statistically insignificant

*Terminal Building cost does not include Landside or Airside Civil Site or Costs associated with the Quick Turn Around Facility

Terminal Building – 2018

$80.3M*Slide14

Master Schedule

14

ActivityStart

FinishEnabling Demo27-Mar-17 A06-Nov-18

Quick Turnaround (QTA)12-Apr-17 A15-May-19RTR Cable Relocation14-Feb-18 A04-Mar-19

Civil Landside15-Feb-18 A07-Oct-21

Terminal Sitework14-Dec-17 A03-Apr-19

Terminal 13-Dec-17 A25-Mar-21

Civil Airside14-Dec-17 A15-Jul-21RTR Facility15-Jan-18 A12-Mar-20

Landscaping04-Jan-2113-Oct-21Slide15

CMAR Coordination30% Cost Estimate Reconciliation

Design Coordination Constructability ReviewsProgress Estimates GMPMultiple Packages to Coordinate with Funding Schedule Timing and Procedures Multiple GMPs based on bid packagesIGMP at 90% design

15Slide16

Next 60 days

Environmental Assessment - FONSI – May 1st Release Enabling Demo and QTA Packages for bidReview Terminal Airside Package Review Terminal Building Package Schedule Funding Meeting with LADOTDReview QTA Design with Rental Car Agencies RTR Cable Relocation Bid by CMAR

Estimate and Reconciliation with CMAR/RS&HPotential RFP Selection for short term financing 16