/
LIU-SPS I mpedance Reduction: LIU-SPS I mpedance Reduction:

LIU-SPS I mpedance Reduction: - PowerPoint Presentation

studyne
studyne . @studyne
Follow
342 views
Uploaded On 2020-08-04

LIU-SPS I mpedance Reduction: - PPT Presentation

Deployment Strategy Possible S ynergies with aC Coating P Cruikshank on behalf of TEVSC with many inputs from LIUSPS team LIUSPS 26 August 2015 Paul Cruikshank 1 Impedance Reduction Deployment ID: 797849

sss mba amp mbb mba sss mbb amp sps impedance transport reduction august liu arcs coating ls2 arc cruikshank

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "LIU-SPS I mpedance Reduction:" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

LIU-SPSImpedance Reduction:Deployment Strategy,Possible Synergies with a-C CoatingP. Cruikshank on behalf of TE/VSCwith many inputs from LIU-SPS team

LIU-SPS, 26 August 2015

Paul Cruikshank

1

Slide2

Impedance Reduction DeploymentDeployment strategy is shaped by the following inputs:Needs & priorities for impedance reduction,Recommendation of C&S review to move a-C coating to LS3Output of scrubbing reviewAvoid to remove same object twice for impedance and a-CAvoid to reopen vacuum system twiceConflicts with YETS, EYETS, LS2 co-activities & transport.ALARA constraintsImpedance reduction technical solutionsOptimisation of costs & manpower.Validation of technical solution via pilot project

LIU-SPS, 26 August 2015

Paul Cruikshank

2

Slide3

Impedance reduction in arcs – overview & needsLIU-SPS, 26 August 2015Paul Cruikshank3

MBB

MBB

MBA

MBA

QF

SSS

MBA

SSS

QD

MBB

MBB

MBA

MBA

SSS

QF

Cells

% SPS

Chamber type

X-section (mm)

Form

Units /cell

Chamber (mm)

Chamber /cell

% cell

% SPS

84+12 Arc+DS

88.9

MBA

152 x 36.5

Rect

4

6660

26640

41.6

37.0

MBB

129 x 48.5

Rect

4

6640

26560

41.5

36.9

QF mag

152 x 38.3

Elipse1334633465.24.6QD magDia 83Round1334633465.24.6QF SSS152 x 36.5Ellipse1205220523.22.8QD SSSDia 83Round1205220523.22.863995100.088.9

P1

P2

Slide4

Impedance reduction of SSSLIU-SPS, 26 August 2015Paul Cruikshank4

MBB

MBB

MBA

MBA

QF

SSS

MBA

SSS

QD

MBB

MBB

MBA

MBA

SSS

QF

Displace 16 SSS

QF

per arc

Treatment underground or ex-situ

Several different chamber configurations

Provides access to QF & MBA

extremity

Priority 1

Priority 2

Displace 16 SSS

QD

per arc

Treatment underground or ex-situ

Several different chamber configurations

Provides access to QD and MBB extremity

Slide5

SSS Impedance Reduction ConsiderationsAvoid LS2 co-activitiesTreat priority P1Early pilotLIU-SPS, 26 August 2015

Paul Cruikshank

5

1

2

3

4

5

6

Meyrin, P1 LHC

(magnet lift)

Prevessin

(magnet lift)

RF

(LS2)

TT40

ext

TT20

ext

Future dump?

(LS2)

Injection

Dump

TT60

ext

ECX5

BHA5

(magnet lift)

Heavy transport in arcs 3-4 and 4-5 during LS2 is restricted if

b

eam dump (civil engineering) goes ahead

→ Impedance reduction campaign of SSS

QF

& QF in

arc

s

3-4 & 4-5 during EYETS

→ Remaining 4

arc

s

in LS2.

→ Impedance reduction of SSS

QD

& QD could be applied in same way

Slide6

Impedance reduction costs (without transport) LIU-SPS, 26 August 2015Paul Cruikshank6

Costs courtesy of

J.Perez

-Espinos

.

Transport

costs

are

included

in

a-C study (see later).

‘Working line’ cost in

r

ange 844k to 1213k

Slide7

What about a-C coating?Awaiting SPS scrubbing review for needs & prioritiesa-C coating solution (ex-situ) validated on dipoles & quadsa-C cost estimate made for full and partial coating variantsSynergies between a-C & impedance reduction addressedBut,Until technical needs are confirmed, deployment options are numerous and inter-related.→ Assume a working line for impedance reduction→ Assume a working line for a-C coating LIU-SPS, 26 August 2015

Paul Cruikshank

7

Slide8

a-C partial coating & impedance reductionWorking line for a-C coating (pending scrubbing review + validation long cathode) LIU-SPS, 26 August 2015Paul Cruikshank8

MBB

MBB

MBA

MBA

QF

SSS

MBA

SSS

QD

MBB

MBB

MBA

MBA

SSS

QF

MBB

MBB

MBA

MBA

QF

SSS

MBA

SSS

QD

MBB

MBB

MBA

MBA

SSS

QF

a-C

a-C

a-C

a-C

+

Imp’d

a-C

+

Imp’d

a-C

+

Imp’d

a-C

a-C

+

Imp’dIn-situMBBMBAMBAQFSSSMBASSSQDMBBMBBMBAMBASSSQFMBBIn-situIn-situIn-situEx-situEx-situEx-situEx-situIn-situ≤ LS2LS3 *ImplementationProposal

Slide9

a-C & impedance reduction of SSSQF & QF in EYETS/LS2LIU-SPS, 26 August 2015Paul Cruikshank9

MBB

MBB

MBA

MBA

QF

SSS

MBA

SSS

QD

MBB

MBB

MBA

MBA

SSS

QF

MBB

MBB

MBA

MBA

QF

SSS

MBA

SSS

QD

MBB

MBB

MBA

MBA

SSS

QF

a-C

+

Imp’d

→ Combined impedance reduction & a-C coating activity

→ Vacuum

system only opened once at QF/SSS

QF

zone

SSS transport costs are shared (16 SSS

QF

per arc)

In-situ a-C of QF to be studied & validated (pumping 63 m string)

Activity split between EYETS (2 arcs) & LS2 (4 arcs)→ Other VSC consolidations could be combined (sector valves, ion pumps)a-C+Imp’da-C+Imp’da-C+Imp’d

Slide10

a-C factory optionsLIU-SPS, 26 August 2015Paul Cruikshank10

BA2 lift

BA3 lift

BA6 lift

BA4 crane

BA5 crane

Transit

Transit

aC

ex-situ factory

ECX/ECA5

TCC6

Other ?

aC

in-situ factory

aC

ex-situ factory

BHA5

Other ?

aC

ex-situ factory

B867 via BA3 & road

P1.8 via BA6 & road

B?? via road

Other ?

192 SSS

192 Quad

744 MB

Tunnel transport

Surface transport

Underground activity

Surface activity

aC

typical sequence:

Disconnect (

vac

+

mech

)

Transport

Clean +

aC

coat

Transport

Survey (

x,y,z,tilt) Reconnect (vac + mech Survey (smoothing)BaselineAdjacent quads can’t besimultaneously removed

Slide11

a-C cost estimate details and variantsLIU-SPS, 26 August 2015Paul Cruikshank11

Many inputs from VSC, TE-MSC, EN-SU, EN-HE, LIU-SPS team

Slide12

Cost for a-C variants, 29/04/2015 (full, partial, 1 arc):Preliminary totals

LIU-SPS, 26 August 2015

Paul Cruikshank

12

Working line is to implement a-C in one arc during LS2

Cost to

aC

coat QF and

SSS

QF

for

6 arc

s

~ 1220

kCHF

(400

kCHF

is transport)

Slide13

Impedance reduction - PlanningEYETS starts in December 2016Manufacturing of new components must start early 2016 (~ 9 months duration)Impedance solutions need to be confirmed in coming monthsDetailed designs completed and validated by end of 201532 SSSQF to treat in 12 week intervention (my assumption)4 per week = 8 weeks2 weeks to complete first assembly

2 weeks to reclose/repump/debug.

Assume SSSQF to surface as valid pilot for remaining arcs and

aC

needs

Arcs 3-4 & 4-5 as working line

If via BA3, then SSS

QF

transport to

867

.

Will require ~ 50 m2 for activity, plus ~ 50 m2 for

handling

Not excluded that SSS

QF

treated underground (

eg

ECX5) if

aC

not requiredRetrofit of shielding or new

chambers depends on impedance resultsParallel activity in tunnel to treat QF & MBA extremity where required

Experience will dictate how to execute for future arcs

a-C coating needs not yet known…..LIU-SPS, 26 August 2015

Paul Cruikshank

13

Slide14

Extensive SPS radiation campaign Feb 2013 for LS1:MB range 0.1 - 100 uSv/hr @ 40 cmQuad & SSS range 1 - 1000 uSv/hr @ 40 cmNeed to make detailed assessment for each SSSQF, SSSQD, QF, QD to treat Dose ‘cost’ for each item

to be treated – list to compile

Public road limitations < 5 uSv

/

hr

– otherwise ‘transport containment’ required

Avoid road

transport (minimize transport)

Impedance reduction - Radiation

considerations

LIU-SPS, 26 August 2015

Paul Cruikshank

14

Sextant 5

(best)

Sextant 1

(worst)

Slide15

SummaryWorking line has been assumed for impedance reductionPriority 1 is SSSQF zone = 2 arcs is EYETS, 4 arcs in LS2SSSQF will cost 844 k to 1213 k (+400 k transport if no a-C)SSSQD will cost 130 k to 1116 k (+0k transport if combine with a-C in LS3)2 arcs in EYETS avoids LS2 co-activities and provides pilot.Working line has been assumed for a-C coatinga-C coating of SSSQF and QF for 6 arcs = 1220 kCHFPartial a-C coating of 1 arc in LS2 = 1763

kCHFPartial a-C coating of 6 arcs in LS3 = 4656 k

CHF Impedance reduction & a-C synergies

Deployment of both activities EYETS, LS2, LS3 seems compatible

Transport costs can be shared

Opening of vacuum system can be optimized

Many variants have been considered and costed

Changes to either working line with impact the other.

LIU-SPS, 26 August 2015

Paul Cruikshank

15

Slide16

LIU-SPS, 26 August 2015Paul Cruikshank16Thanks for your attention !