ADO-PO, TC Meeting 2 th   of May 2016 ADO-PO, TC Meeting 2 th   of May 2016

ADO-PO, TC Meeting 2 th of May 2016 - PowerPoint Presentation

vestibulephilips
vestibulephilips . @vestibulephilips
Follow
343 views
Uploaded On 2020-06-19

ADO-PO, TC Meeting 2 th of May 2016 - PPT Presentation

ATLAS Design Office Activities R Vuillermet 02052016 R Vuillermet EPADOPO 1 Overview Resources Non exhaustive list of technical activities that shall be covered during 2016 in the ATLAS Design office ID: 781290

vuillermet design ado 2016 design vuillermet 2016 ado installation prepare access chambers tatiana tomasz drawings augusto support lifting 2016r

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "ADO-PO, TC Meeting 2 th of May 2016" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

ADO-PO, TC Meeting2th of May 2016

ATLAS Design Office ActivitiesR. Vuillermet

02/05/2016

R. Vuillermet EP-ADO-PO

1

Slide2

OverviewResources

Non exhaustive list of technical activities that shall be covered during 2016 in the ATLAS Design officeConclusions

02/05/2016

R. Vuillermet EP-ADO-PO

2

Slide3

Resources in ATLAS Project Office

Raphaël Vuillermet Design office supervisor

Giancarlo

Spigo

RSO & Project Engineer

Tatiana Klioutchnikova Integration & Project Engineer

Claudio

Bortolin ATLAS cooling activities

Augusto

Sciuccati FEA referee of the Design Office

Marco Ciapetti Tomasz Blaszczyk Julien Migne Wim Van EmdenVit Zahradnik Alexander SeletskiyJamie Pinnel Workshop and Design OfficeGevorg Akhperjanyan Workshop and Design Office Didier Bertet TC support and safetyAntonio Meleddu Training period

02/05/2016

R. Vuillermet EP-ADO-PO

3

Slide4

Non exhaustive list of technical activities that shall be covered during 2016 in the ATLAS Design Office

02/05/2016R. Vuillermet EP-ADO-PO

4

Slide5

BME

BMG

Brackets for BME chambers

BML

BMF

Space for BMG chambers

BMG chambers

(between feet in sectors 12,14)

(

Wim

, Tatiana)

By the end of the year :

Prepare production drawings and fabricate all installation tools

Prepare installation procedure

Prepare welding

operation (layout drawings)

Procure all supporting elements

During

YETS 2016-17

12

chambers

will be installed

02/05/2016

R. Vuillermet EP-ADO-PO

5

Slide6

Access to alignment equipment's inside the toroid feet

(Tomasz, Tatiana)

Once the BMG chamber will be installed, the access to the muon and detector alignment devices will be impossible from sector 13. New access

platform, reachable from sector 11 and 15 will be

installed.

Prepare production and welding

drawings.

Installation

of such platform is foreseen during YETS 2016-17 before installation of BMG chambers.

02/05/2016

R. Vuillermet EP-ADO-PO

6

Slide7

Maintenance of ECT movement system

(Tomasz, Michel)

Create the up to date 3D environment

Develop the access scenario and the necessary tooling to reach the air pad under the ECT for maintenance reasons.

Perform due verification on ECT structure

Prepare maintenance intervention on

the air pad during

YETS 2016-17

02/05/2016

R. Vuillermet EP-ADO-PO

7

Slide8

Engineering support EB lifting beam(Vit

, Augusto, Raphael)

Control the mechanical design of the lifting beamPropose reinforcementOrganise load and reception test for a usage on 18

th of May

02/05/2016

R. Vuillermet EP-ADO-PO

8

Slide9

Define the layout

and envelope drawings for each chamberDefine the length of optical fibbers

Define the routing of all services, allocated cable trays up to USA 15

Study and prepare installation tools and access

Integrate the alignment elements

Total number: 16 chambers

(MDT

+

RPC)

BIS7/8 chambers

(SMDT + RPC)

(Alexandre, Tatiana)02/05/2016R. Vuillermet EP-ADO-PO9

Slide10

Optimize the

required intervention schedule with a mixt of in-situ electronic replacement and chambers extraction

BIS

BIL

BI project studies

(Tatiana)

02/05/2016

R. Vuillermet EP-ADO-PO

10

Slide11

nJD/nSW project

Status The nJD/nSW

design is finished and tendering process is on going.Remaining tasks:

Prepare calculation note to justify the design (Augusto)Prepare set of tendering and production

drawings, nJD, nSW, KM

(Julien, Jamie)

Finalize

the design of the movement system

(Tomasz

)

Finalize the design

of the transport and lifting system, prepare tendering document, prepare FDR on 21st June 2016 (Vit, Raphael, Augusto)Design the assembly and installation tooling (Marco, Julien, Jamie, Antonio)Finalize the design of the services bracket (Alexandre)Update layout drawings of building 180 and b191 for assembly (Julien)02/05/2016R. Vuillermet EP-ADO-PO11

Slide12

ITK

Steer the engineering development of the scale one mock-up based on the spare Inner Warm Vessel.Define the rail supports and procure them (Antonio, Augusto)

Follow the engineering development of positioning and clamping tool for welding operation

(Augusto, Raphael)Organize the logistic for the welding operation

(Augusto, Raphael)

Installation scenario

Make proposals for the ITK lifting tool

(Tomasz)

Design the interface between the Outer Cylinder and the rail support, once the OC design would have progressed (fall 2016)

(

Augusto, Raphael)

Prepare insertion test during LS2 (Tomasz)02/05/2016R. Vuillermet EP-ADO-PO12

Slide13

General engineering activities

ECT tower – Design an access platform in sector 5 that can be easily installed for temporary access. (Wim

)Re-think the routing of cables for the VT motorisation, to remove the risk of damaging them during the JFC2 removal (

Marco)

Update drawings to procure the lifting cylinder

for the SW

lifting

frame

(Marco

)

Design and fabricate new handrails extension for the UX15 level 4 balconies on USA side (Vit)Secure the access hole in sector 13, voussoir level (Gevorg)02/05/2016R. Vuillermet EP-ADO-PO13

Slide14

HF truck, (Gevorg)

Secure the access ladder to avoid the hole in the middle of the balcony Modify the hand rails to give easier access to S13 platformDesign a path for flexible movement services in sect 13 and supports compatible with the nJD/nSW geometry and EB calorimeter.

(Tomasz, Tatiana)

ECT - Redesign of a stiffer ECT Z stopper (HO side)

(?)

Integration of Optical fibber in

LArg

flexible chain in sect9

(Vit, Tatiana)

Design and integrate a support to add optical fibbers into the

Larg

Flexible chain (sect9). This support shall be compatible with the existing geometry and shall minimise its installation time AFT bracket cantilever tool (Wim, Tatiana)Design a cantilever tool to remove the AFT bracket to allow the installation of BIS7&8 during LS2.02/05/2016R. Vuillermet EP-ADO-PO14

Slide15

Update of Muon layout drawing with chambers installed during LS1: BOE and BME in sector 13

(Gevorg) EEL

, EES – Creation of simplified models for integration study purposes

(Gevorg)

HF

Trucks:

integrate new routing of service

pipes for traction system

(Gevorg

)

Correction of muon chambers by

sectors (Tomasz, …)Update beam pipe layout for run and standard opening (Alexandre)Update General ATLAS layout drawings with LS1 beam pipe sections (…)Create ITK enveloppe layout (…)CAD improvements(Tatiana, Alexander, Gevorg, Vit

, Tomasz, Wim

)

02/05/2016

R. Vuillermet EP-ADO-PO

15

Slide16

B180 technical support

Logistic and technical support for the preparation of

sTGC

assembly clean room in b180.

(Didier)

Installation and adjustment of assembly

marbles

Installation and procurement of equipment before the arrival of the assembly team at the end of 2016.

Logistic in b180 :

(Didier)

Configuration of the hall for installation of ITK scale one mock-up and nSW assembly area

Reorganisation of the “bolt store” in the fence area. If you need fasteners, think to look first their before ordering …02/05/2016R. Vuillermet EP-ADO-PO16

Slide17

Conclusion

For YETS 2016-17 many engineering studies have

to be finalised to went into production for their installation

during next YETSBMGAccess platform to alignment system

ECT access to movement system

Development effort will

continue for upgrade program for

LS2 and LS3:

Design of installation tooling for the nJD/nSW and sector assembly shall be well advanced and ready to go in production.

Tendering

of the nJD/nSW lifting and transport tooling shall have started

Definition of the BIS7&8 ITK - Preparation of scale one mock-up(s) in b180.ITK - Definition of lifting tools and design of the guiding and support systemOptimization of the BI schedule and preparation of the TDR02/05/2016R. Vuillermet EP-ADO-PO17