/
NSLS-II Transition  to Operations NSLS-II Transition  to Operations

NSLS-II Transition to Operations - PowerPoint Presentation

calandra-battersby
calandra-battersby . @calandra-battersby
Follow
347 views
Uploaded On 2018-11-09

NSLS-II Transition to Operations - PPT Presentation

Erik D Johnson Deputy ALD for Programs Science Advisory Committee April 4 2011 Science Program Goals 1 Very fast ramp up of science program 2 Continuous service to user community 3 Dramatically advanced capabilities and high productivity ID: 724343

operations transition nsls commissioning transition operations commissioning nsls project amp facility phase installation readiness plan accelerator defined authorization documentation

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "NSLS-II Transition to Operations" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

NSLS-II Transition to Operations

Erik D. Johnson, Deputy ALD for ProgramsScience Advisory Committee April 4, 2011Slide2

Science Program Goals:

1) Very fast ramp up of science program2) Continuous service to user community

3) Dramatically advanced capabilities and high productivity

Transition to NSLS-II operations involves evolution from NSLS operation and NSLS-II construction to NSLS-II operation, all the while continually hosting a large user community and renewing the scientific facilitiesMust develop a substantial number of beamlines and transition staff and users from NSLS ops to achieve maximum scientific productivity as soon as possibleRequires coordinated planning for a portfolio of activities

Science Capabilities at CD-4 and BeyondSlide3

NSLS-II Project

Defining Transition to Operationsfor NSLS-II Project and for NSLS-II Facility

CD-4

Projected Early Finish

Facility Transition to Operations Period

NSLS Operations

NSLS-II OperationsSlide4

Key questions for Transition to OperationsFrom several different perspectives ask:

What do you have? Validation of attainment of project scopeAnalysis of safety performance/ hazards Who is responsible for operating it?What organization accepts responsibility for operationsWhat is the span of their responsibilityWhat will it take to operate it?Operating procedures, training, documentationFinancial planning (Operation, Maintenance, Improvement)Slide5

Approach

Many elements moving in and out of portfolioEstablish framework for integration of portfolio: Facility Transition to Operations (FTOP)Standard process for transfer of projects to facility operationsDefine interfaces, interdependencies and coordination requirements

TOP documentation specific to each project: Project Transition to Operations (PTOP)

Work under umbrella of standard process and feed into FTOPTailor PTOP documents specific to needs of each projectSlide6

Facility Transition to Operations Plan (FTOP)

Programmatic transition of entire NSLS-II facilityA comprehensive plan to manage the smooth integration of the transitions from construction to operations (NSLS-II, NEXT, NxtGen, NIH, etc) and from operations to decommissioning (NSLS) for the entire NSLS-II Facility during the years FY12 to FY15Describes facility goalsIdentifies and integrates transition activities (scope)

Including planning assumptions

Aligns schedule and key milestonesIdentifies interfaces, interdependencies, and coordination requirementsDocuments overall resource plan Describes organization and managementCatalogs supporting documents Draft prepared – to be kept current through out transition periodSlide7

NxtGen Transition to Operations

Relationship of TOPsFTOP: Coordination of Portfolio

Integration and alignment of projects

Operations organizationFinancial planning (Operation, Maintenance, Improvement)PTOP: Project CloseoutOutlined for NSLS-II in PEPRequired by DOE O 413.3 prior to CD-4Validation of attainment of project scope

Analysis of safety

performance & hazards

Operating

procedures, training,

documentation

Photon Sciences Portfolio Facility Transition to Operations Plan

NEXT Transition to Operations

NSLS-II

Project Transition to Operations Plan

Children

(Project TOP

)

Parent (Facility TOP)Slide8

DOE G 413.3-16 Project TOP elementsSuggested elements (not requirements)

Facility Support, Op’n & Maint TrainingEMS and QA Documentation PlanSafeguards and Security Documents

Permits/Licenses

Authorization and NotificationProject Transfer to OperationsBusiness FunctionsProject Information and Records TurnoverTransition to Operations ReportingUser/Operating Staff PlanningLessons Learned

Project De-staffing Plan

Project Description

Planning Management

DOE Orders and Guidance

Key Transition Phase Steps

Strategy

Operation Cost

Organization/Stakeholder Interface

Transition Team

Configuration Control

KPP’s and Completion criteria

Schedule and Key Milestones

Readiness ReviewsOperations and Maintenance ManagementMost items are well defined and in many cases well advancedItems most in need of further development relate to operations (FTOP elements in our approach)Slide9

NSLS-II Project Transition to Operations

Planning documents for Installation and commissioningBORE planConventional Facilities Commissioning PlanInfrastructure Systems Operations & Maintenance Responsibilities Accelerator Commissioning PlanTask Force on Commissioning of Accelerator Complex

Linac Commissioning Plan

Booster Commissioning PlanBeamline Readiness PlanSafety Documents in preparationLinac Commissioning Safety Assessment Document (SAD) & Accelerator Safety Envelop (ASE)Booster Commissioning SAD & ASEStorage Ring Commissioning SAD & ASEAbove 3 will be combined to form NSLS-II Operations SAD & ASESlide10

Integrated Transition Management Team

Integrated Transition Management Team (ITMT)Develop & manage transition plans and documentation

Ensure all interfaces are identified, defined, and managed

Ensure ES&H and QA goals are achieved for transition activitiesSupport the preparation, review, and approval of project documentation, including closeoutIdentify and manage transition related risks and issuesCore members appointedAesook Byon, Diane Hatton, Steve Hoey, Erik JohnsonITMT will form working groups and task forces for particular topical areas

BORE, Installation, Commissioning, ARR

Will draw from Photon Sciences Directorate and more broadly when needed

Erik Johnson appointed overall Facility Transition to Operations Manager

Lead the ITMT

Point of contact for matters relating to implementation of transition

Hold regularly scheduled transition meetings

Keep PSD management informed in timely mannerSlide11

Authorization Basis Processes

That assure all hazards are identified and controlledAll necessary documentation is in placeFacilities are complete and turned overEquipment is installed and operationalAll staff is properly trained and qualifiedDefines the envelope of safe operation/commissioning

Phased Commissioning (Linac, Booster, Storage Ring, Final Ops)

Applies to documentation, readiness reviews & commissioningResources identified to coordinate the processesMilestones for each module are defined in scheduleSlide12

Achieving Authorization BasisSlide13

Authorization Process for each Module

Steps in each of the four modules are essentially identical:Complete necessary BORE’sInstall and test equipmentEquipment/Instrument Readiness Reviews Develop and obtain approval of Authorization Basis DocumentationDevelop Authorization Plan

Implement operational controls (training, procedures,

etc)Develop specific commissioning plansAccelerator Readiness ReviewBegin commissioning/final opsSlide14

Beneficial Occupancy & Installation

LOB 1 Phase 96/1/12LOB 2 Phase 85/1/12

LOB 3 Phase 10

6/29/12 Phase 23/23/11Phase 35/18/11

Phase 1

2/1/11

Phase 5

9/27/11

Phase 4

6/2/11

Phase 7

2/9/12

Phase 6

11/28/11

Successful BORE’s required to allow installation of technical equipment

10 BORE’s broken into logical construction phases

First BORE completedNow every month or two until 6/12Slide15

Conventional Facilities Transition Activities

Integrating Operations & Maintenance (O&M) organization (BNL Facilities & Operations) in start-up and commissioningEventual stewards gain experience with equipmentEquipment vendors interface with ultimate ownersVerify technical performance is achievedIndependent Commissioning Contractor Internal design and O&M staff involved in validation

Oversee occupancy/ASD installation phase operational requirementsSlide16

Accelerator Installation Status

Installation schedule 95% complete, including resource loadingSurvey work occurring full timeSite access plan & PPE requirements establishedWork control coordinators all completed trainingTemporary cages for staging are completed

P1 utility piping about 40% complete

P1 cable tray ~40% completeElectrical installation under wayAssigned riggers and electricians in placeTechnical installation supervisors for each ASD group assignedSlide17

Authorization Basis Documents

Accelerator Safety Envelope (ASE) defines the “envelope of safe operations”Safety Assessment Document (SAD) provides the hazards analysis and supporting criteria for the ASESAD and ASE developed for each phaseFollow DOE Order 420.2BPreliminary SAD (for CD-3) approved by DOE 2008Final LINAC Commissioning SAD and ASE complete and currently in review stageSlide18

Accelerator Commissioning and Operation AuthorizationSlide19

Accelerator Readiness ReviewsSuccessful ARR’s are required for permission for Accelerator Commissioning

Four ARR’s will be conducted as per Authorization Bases Strategy (LINAC – 11/11, Booster – 12/12, Storage Ring – 05/13, Final Ops – 08/13)ARR Process is well defined in DOE 420.2-1Systems and procedures established to address credited controls (SAD and ASE), documentation requirements, and personnel qualificationNot a facility inspection

BORE will address facility space readiness

Equipment/Instrument review process will address equipment installation readinessNSLS-II ARR Coordinator assignedARR Team appointed three to four months prior to first scheduled ARRWill be a mix of BNL, BHSO and external expertsMost review accomplished before site visit (website, conference calls)On-site ARR when we are READY“An ARR is not a method for achieving readiness, but for

verifying

it.” (DOE G 420.2-1)

Maximum one week on siteSlide20

Beamline Readiness at CD-4

Beamline subsystems installed and tested (without beam), including enclosures, beam transport, personnel protection system (PPS), and associated equipment protection system (EPS), utilities, & controls systemsMain beamline optical systems installed and associated mechanics testedDiagnostic instrument installed at endstation to enable beamline commissioningBeamline safety configuration review & walkthrough completedBeamline readiness report submitted to Experimental Facilities DirectorSlide21

Project Performance and Completion Criteria

Defined in the Critical Decision Approvals and also refined inGlobal requirements Document Defined minimum goals for each stage of commissioning, prerequisite to starting next stageStart-up Test Plan Defined criteria for completion of commissioning stagesNSLS-II Project Key Performance Parameters

Key Parameters

PerformanceConventional FacilitiesBuilding Area>340,000 GSF

Accelerator Facilities

Electron Energy

3.0

GeV

Stored Current

25

mA

Experimental Facilities

Beamlines

installed and ready for commissioning with X-Ray Beam

6Slide22

NSLS-II Project Closeout Report

Target date: October 2014Technical, scope, cost and schedule baseline accomplishmentsFinancial closeout, including a final cost reportCloseout approvalsContract closeout statusAdjustments to obligations and costs

Photographic documentation

Baseline change control logSlide23

SummaryFramework established for FTOP and PTOPs

Integrated Transition Management Team establishedNSLS-II PTOP well defined and advancing on scheduleAuthorization processes well defined and on scheduleCoordinators and working groups identified and in placeBORE process underwayInstallation and Commissioning Plans well developedARR team to be established in FY11Starting to prepare for project closeout