Excelsior Gateway Beautification Project: Excelsior Gateway Beautification Project:

Excelsior Gateway Beautification Project: - PowerPoint Presentation

ellena-manuel
ellena-manuel . @ellena-manuel
Follow
399 views
Uploaded On 2017-04-19

Excelsior Gateway Beautification Project: - PPT Presentation

Ever Upward Nicole Agbayani Corridor Manager Excelsior Action Group Isis Rodriguez Artist sculpture design Jason Gilmore Artist mosaic design November 5 2012 Excelsior Action Group est 2002 ID: 539336

design 000 excelsior 2012 000 design 2012 excelsior community project mosaic fabrication 2013 phase fee group corridor action 500

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Excelsior Gateway Beautification Project..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Excelsior Gateway Beautification Project: Ever Upward

Nicole Agbayani, Corridor Manager, Excelsior Action Group

Isis Rodriguez, Artist, sculpture design

Jason Gilmore, Artist, mosaic design

November 5,

2012Slide2

Excelsior Action Group, est. 2002

Our mission is to revitalize the San Francisco Excelsior Neighborhood’s Commercial Corridor by involving residents, merchants, neighborhood associations and city agencies through activities aimed to reinvigorate, green, beautify, strengthen and unify our diverse community.Slide3

Project BackgroundSlide4

Community Design ProcessSlide5

Conceptual DesignSlide6

Metal SculptureSlide7

Mosaic ColumnSlide8

Project Workplan

Budget: $40,000

$30,000 Community Challenge Grant

$10,000 OEWD Capital Improvement GrantIn Kind support: Community volunteers mosaicTimeline: February 2012 – September 2013Design phase (Feb 2012 – Oct 2012)

Approval phase (Oct 2012 – May 2013)

Fabrication & Installation phase (Jun 2013 – Sep 2013)

Ever Upward Project

Budget Detail

  Description  Amount 

a.  Design Fee - Isis Rodriguez  $3,000.00

b

.  Design Fee - Jason Gilmore  $700.00

c

.  Engineering Fee - SDE  $4,000.00

d

.  Metalwork fabrication  $13,000.00

includes painting ($1,600.00)

c

.  Column  $6,500.00

 

fabrication

 

 

transport

 

 

footing

 

 

foundation

 

 

installation

d

.  Permits  $1,500.00

e

. Mosaic tiles  $2,000.00

f

.  Materials for mosaic  $300.00

g

.  Fiscal sponsorship  $6,000.00

h

. Contingency  $3,000.00

     

  TOTAL  $40,000.00 Slide9

Thank You!

Nicole Agbayani, LEED AP BD+C

Corridor Manager, Excelsior Action Group

(415) 585-0110 nagbayani@eagsf.org