/
PIP Update PIP Update

PIP Update - PowerPoint Presentation

kittie-lecroy
kittie-lecroy . @kittie-lecroy
Follow
371 views
Uploaded On 2017-01-30

PIP Update - PPT Presentation

Nov 1 9 th 2014 Agenda Summary Update Current Activities Updates Ken Domann PIP Schedule and Budget Ryan Crawford Anode Supplies amp Transformers Pat Sheehan Bias Supplies Ferrites ID: 515759

pip booster amp update booster pip update amp linac supplies testing ryan review beam plan cavities budget working john

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "PIP Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

PIP Update

Nov

1

9

th

2014Slide2

Agenda

Summary Update

Current Activities

Updates

Ken

Domann

- PIP Schedule and Budget

Ryan

Crawford - Anode Supplies & Transformers

Pat Sheehan - Bias Supplies / Ferrites

John

Reid / Matt

Slabaugh

- Booster RF Refurbishment

Dave

Johnson - Laser Chopper Power & Test Slide3

Update

Power switch wreaking havoc

Linac

SBK

: Progressing –

Fernanda inspecting SLAC

for certification testing

Linac LN:

Final

Fiber Amp

still being worked on – Early Nov delivery

date – Possibility to test

Linac Modulator

:

Parts for

53-cell prototype are

arriving –

high-priority to finish

Booster

Beam

:

Cogging

– plan to finish in December

Invesitgating

VIMIN fluctuations

Booster RF:

Booster

RF5 in

testing

Update from John / Matt

Station 20 – Prep underway

Stations 21 & 22 being planned – cavities should be ready in FY16

15

Hz testing

mostly on hold

Perpendicular Cavities – working on design – having regular meetings

Booster

Anode Supplies

update from Ryan

C

Booster

Bias supplies

update from Pat

Sheahan

Booster

Shielding:

TLM installed and collecting data – modules being built and will be installed

Booster Transformer:

East Install

update from Ryan C

Booster Absorber/Kicker:

Running

on new short kickers

New configuration with insert

   Slide4

Updated October 7,

2014 by K Gollwitzer

Next one

Dec. 2?Slide5

Recent PIP Budget/News

FY15 Budget:

No issues with spending $$

now – we should be at full speed

Lab upload should be

complete – but not reported back

PIP working on RLS

for changed tasks (SBK, new cavities)Meetings to discuss transition PIP to PIP-II continue

DOE REVIEW of PIP in Jan!! Managers may give talksExpect a 1.5 – 2 day review on PIP and 700 kW plans

Good quality review committee

AAC recommendations

Proceed with the plan to replace the obsolete modulator hardware in the

Linac

.

Develop a plan that itemizes beam loss reduction steps to maintain present levels of beam losses as the intensity doubles. Keep a focus on the laser notching program to demonstrate the feasibility of the system and its reliable operation.