/
Case Studies in Contract Close Out Audits Case Studies in Contract Close Out Audits

Case Studies in Contract Close Out Audits - PowerPoint Presentation

lois-ondreau
lois-ondreau . @lois-ondreau
Follow
353 views
Uploaded On 2018-11-09

Case Studies in Contract Close Out Audits - PPT Presentation

May 2014 J eff Witt CPA CIA CCA CFE MCSE Jeff is a Senior Manager in Moss Adams Construction Audit amp Advisory Services Practice with over 18 years of accounting experience His focus is on performing efficient construction contract audits based on detailed planning and risk ass ID: 724990

contract change orders case change contract case orders payment final study owner contractor cont costs lien releases cost waiver

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Case Studies in Contract Close Out Audit..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Case Studies in Contract Close Out Audits

May 2014Slide2
Slide3

J

eff Witt,

CPA

, CIA, CCA, CFE, MCSEJeff is a Senior Manager in Moss Adams’ Construction Audit & Advisory Services Practice with over 18 years of accounting experience. His focus is on performing efficient construction contract audits based on detailed planning and risk assessment that focus on those aspects of contract compliance that are of greatest risk to our clients. Prior to joining Moss Adams, Jeff was a Controller for a government contractor where he led the implementation and control of compliant systems for government contracting. He also served as a government auditor for the Defense Contract Audit Agency for 10 years.

Presenters

Steve Fineberg

,

CPA

, CIA

,

Steve is a Senior Manager in his eighth year with Moss Adams’ Construction Audit & Advisory Services

Practice

and brings over ten years of relevant experience in capital project program controls, forensic investigation, accounting and financial services. Steve has managed numerous capital project performance

audits

including various engagements that were subject to Generally Accepted Government Auditing Standards (GAGAS) requirements. He has managed several large performance audits, and has served as a project manager with responsibility for leading all aspects of contract compliance testing.Slide4

Agenda

Discuss case studies related to common construction contract close out situations including:

Change orders

Contract complianceOther closing issuesQuestionsSlide5

Common Causes of Problems During Contract Close Out

No 5

. Improperly

executed lien releasesNo. 4 Subcontract costs not adjusted for subcontractor change orders, including deductive change ordersNo. 3 Reconciliation of final job cost reports to final payment applicationNo. 2 Contract terms not followed during contract performance No. 1 Unresolved change order issuesSlide6

Case Study on Improperly Executed Lien Releases

Background

Conditional waiver on progress payment

- This waiver generally specifies that if the contractor has been paid, the waiver is an effective proof against any lien claim on the property.Unconditional waiver on progress payment - This waiver unconditionally releases all claimant rights through a specific date.

Conditional waiver on final payment - This waiver releases all claimant rights to file a lien if

they have been paid to date. Unconditional final waiver final payment

– In general, this

waiver

unconditionally

releases

all

rights of the claimant to place a

lien

on the owners

property.Slide7

Case Study on Improperly Executed Lien Releases (cont.)

Background (cont.)

If

an owner has a general contractor (GC) that fails to pay subcontractors, suppliers or laborers or neglects to make other legally required payments, those who are owed money can look to the owner of the property for payment, even if the owner paid the contractor in full.Slide8

Case Study on Improperly Executed Lien Releases (cont.)

Background (cont.)

California Preliminary Notice (CA Civil Code sections 8100-8118) requires subcontractors to alert owner.

Owner will want to make sure it has lien releases before any payments to GC related to these and others (some not required to provided notice to owner).Slide9

Case Study on Improperly Executed Lien Releases (cont.)

Audit Steps

Auditors determined for which subcontracts the lien releases were not obtained.

Auditors alerted owner and indicated that final payment should not be made until resolved.ConclusionLien releases were obtained prior to final payment to contractor, thereby protecting the owner.Slide10

Case Study on Improperly Executed Lien Releases (cont.)

In this case, some lien releases were not obtained (provisional or final) but the owner made payment to the contractor throughout the period of performance.

This subjected the owner to unnecessary risk.Slide11

Case Study on Subcontract Costs Not Adjusted for Subcontractor Change Orders

Background

We frequently note that general contractors are careful to pass through any subcontractor change orders for increased cost, but not so careful when it comes to deductive change orders.

In this case, the general contractor submitted a final payment application. The payment application included the subcontractor costs and any additive change orders.There were no deductive subcontractor change orders included in the payment application.Slide12

Case Study on Subcontract Costs Not Adjusted for Subcontractor Change Orders

Audit Steps:

Obtained a listing of subcontracts and reviewed the subcontract files, including the base award and any subcontractor change orders.

Identification of certain deductive subcontractor change orders that were not included in the job cost detail and not included on the final payment application.Conclusion:The contractor confirmed that these deductive change orders should have been passed on to the owner.

The contractor agreed to modify their final payment application to adjust for these deductive change orders.Slide13

Case Study on Reconciliation to Job Cost Detail

Background

The contract was a Guaranteed Maximum Price (GMP) contract where billings, including the final billing, were to be based on actual, allowable costs.

Contractor included certain estimated costs, not yet paid, in an attempt to expedite final payment and contract close out.Reconciliation of the final payment application to the job cost detail identified the areas of difference (i.e., estimated costs). The estimated costs were not included in the job cost detail (JCD).Slide14

Case Study on Reconciliation to Job Cost Detail (cont.)

Audit Steps:

Reconciliation of final payment application to JCD

Identification of differencesFollow up with contractorConclusion:Contractor provided additional information on negotiation with subs that resolved most estimated costs.

The remainder was a negotiation item that resulted in an adjustment to final reimbursable cost.Slide15

Case Study on Compliance with Contract Terms

Background

A number of specific contract terms were included in the contract including:

AllowancesContingenciesStipulated rates

Specific language concerning costs included in burden rate

Change orders not negotiated as lump sum GMP increasesSlide16

Case Study on Compliance with Contract Terms (cont.)

Background (cont.)

The contractor did not account for some of these terms in accordance with the contract including:

Non lump sum change order costs not separately accounted for.Allowances did not result in correct adjustment to GMP.

Owner contingency usage was not approved in accordance with the contract.

Duplicated costs resulted from billing at stipulated burden rates and separately billing the related costs.Slide17

Case Study on Compliance with Contract Terms (cont.)

Background (cont.)

The contractor indicated it had verbal discussions with the owners rep where the rep approved the departure from contract terms for:

Handling of change orders.Non true-up of allowances.

Usage of contingency.

However, there was nothing in writing to substantiate these claims and the owners rep indicated the contractor was mistaken.Slide18

Case Study on Compliance with Contract Terms (cont.)

Audit Steps:

Identification of contract non compliance issues.

Quantification of amounts involved.Conclusion:Significant adjustments were required to:

GMP limits

Allowable costSlide19

Case Study on Change Orders

Background

The owner (through their representatives), issued field directives authorizing the GC to proceed with work that was the subject of a potential change order.

There was no resolution of many of the proposed change orders.This was done to:Keep the project on the original timeline.Maintain the relationship with the contractor.

Unfortunately, delaying dealing with potential change orders did not make the issues go away. They had to be dealt with prior to contract close.Slide20

Case Study on Change Orders (cont.)

Audit

Steps:

Evaluation of documentation to support:Basis of proposed change ordersCost

estimate support

Quantity analysisSlide21

Case Study on Change Orders (cont.)

Conclusion:

Exceptions were found for basis, cost estimates and quantities.

Owner had to engage in a difficult negotiation process that ultimately resulted in significant cost savings to the owner (versus just approving the proposed change orders).Slide22

Stephen Fineberg, Senior Manager

(916) 503-8175

s

teve.fineberg@mossadams.com Jeff Witt, Senior Manager(503) 478-2282jeff.witt@mossadams.com

Questions?