Michael P Bromfield Construction Engineer NSLSII Conventional Facilities Advisory Committee Review October 5 6 2010 Outline Project Overview LOB Status LOB amp Ring Building Contractor Coexistence Plans ID: 691184

building lob amp ring lob building ring amp coordination contractor construction planning project lobs inspection date mep utilities howell

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "LOB - Ring Building Construction Coordin..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

LOB - Ring Building Construction Coordination

Michael P. BromfieldConstruction EngineerNSLS-II Conventional Facilities Advisory Committee ReviewOctober 5 - 6, 2010Slide2

Outline

Project Overview LOB StatusLOB & Ring Building Contractor Coexistence PlansLOB – Ring Building CoordinationSite Logistics PlanPre-Construction / Mobilization RequirementsActions To Date

Construction Phasing

Inspection Planning

Schedule Status

ConclusionsSlide3

Project Overview

LOB StatusScope (WBS 1.05.03.06)Construction of Laboratory Office Buildings (LOBs) # 1,2 & 3Full Build-Out - LOBs 1 & 3Core & Shell – LOB #2

Temporary Toilets at LOBs 4 & 5, required for Code Compliance

Each LOB features a mix of wet labs, dry labs, fabrication/assembly shops, and technical spaces that have easy access to the Ring Building experimental floor;

Connection of Utility Services from Ring Building, including

Electric, Domestic Water, Sanitary Sewer, Chilled Water, Lab Gases (GN2, CA), Steam & Condensate;

On Site Infrastructure Improvements – Associated Parking & Roads Slide4

Project Overview

LOB Status

Contract amount = $34M

Pre-bid estimate = $43M (Nov. 09)

Contractor selected based on

:

Technical Evaluation Factors

Safety Performance

Technical Experience

Proposed Mgt Team

Proposed Subcontractors

Past Performance & QA

Contractor

Price

Best Value SelectionSlide5

Project Overview

LOB StatusContractor: EW HowellDOE Approval: 8/13/10Contract Award: 9/13/10Notice to Proceed: Est. 10/6/10

Contract Completion Date 6/29/12

LOB 2 Target Beneficial Occupancy Date: 5/1/12

LOB 1 Target Beneficial Occupancy Date: 6/1/12

LOB 3 Target Beneficial Occupancy Date: 6/29/12

Slide6

LOB – Ring Building Coordination

LOB Site Logistics PlanSlide7

LOB & Ring Building Contractor Coexistence Plans

LOB Pre-Construction Efforts Provide LOB 4 Building Pad & Area Grading: 10/1/10Will Facilitate LOB Contractor MobilizationProvide Temporary Electric at Trailer Area: Due 10/8/10Provide LOBs 1-3 Building Pad Turnover Requirements: Due 10/1/10Pads Certified: Survey & Compaction

As-Built Drawings for Underground Utilities

Provide As-built Drawings for LOB Utilities at Ring Building:

Work in Progress by Ring Building Contractor

LOB – Ring Building CoordinationSlide8

LOB – Ring Building Coordination

LOB & Ring Building Contractor Coexistence PlansActions / Discussions To DateCoordination Meeting Held with EW Howell & TorconWill Facilitate Contractor Site UtilizationContractors Share Same Insurance Carrier for CCIP

Will Advise Each Other’s Rep.

EW Howell Plans for Segregating Workers

Take Daily Attendance

Different Color Hard Hat Sticker

Workers Not Shared on Daily Basis

Gated / controlled access to each contractor’s work area Slide9

LOB – Ring Building Coordination

LOB & Ring Building Contractor Coexistence PlansEstablish Weekly Coordination Meetings with both ContractorsContinue to provide As-built information to LOB ContractorHold Safety meetings with LOB ContractorEnsure consistent approach to Inspections

Utilize lessons learned from Ring Building BORE(s) for LOB constructionSlide10

Ring Bldg Construction Phasing

Beneficial Occupancy Dates

Construction of LOBs to be Coordinated with Ring Bldg Construction Phasing

Phase

Milestone

Baseline

1

Pentant 1- BO

1-Feb-11

2

Pentant 5 - BO

9-Feb-12

3

RF Building - BO

23-Mar-11

4

Pentant 2 - BO

2-Jun-11

5

Pentant 3 - BO

27-Sep-11

6

Injection Building - BO

18-May-11

7

Pentant 4 - BO

28-Nov-11

8

Ring Bldg Const.

Complete

30-Apr-12Slide11

LOB 2 Building Pad & Connection Point

Building Pad

MEP Utilities from Service Building

LOB – Ring Building CoordinationSlide12

LOB 1 MEP Connection Point

LOB – Ring Building Coordination

MEP Utilities from Service BuildingSlide13

LOB – Ring Building Coordination

MEP Utilities from Service Building

LOB 1 MEP Connection PointSlide14

Inspection Planning

StaffingConstruction EngineerCivil-Architectural Inspectors - 2Mechanical Inspectors - 2Electrical Inspector – 1 (another to be added)Clerk of the Works / Asst. Project EngineerOrganizationInspectors to be dedicated to specific areas of responsibility

Facilitates Better understanding of area requirements & trade performance

Planning for Inspections more focused on “Interior Finishes”

Ensure Contractor Implements & adequately staffs QA Program

LOB – Ring Building CoordinationSlide15

Inspection Planning, cont’d

Control TestingBy Independent Outside Agencies under BNL contractConcrete TestingSoils TestingStructural SteelStaff can be Augmented as needed by Liro-Gilbane

LOB – Ring Building CoordinationSlide16

Inspection Planning, cont’d

LOB – Ring Building CoordinationSlide17

Inspection Planning, cont’d

Communication and Document ManagementProject Control Software – Contract Manager (formerly Expedition)EW Howell issued licenseEW Howell familiar with Contract ManagerEasily Create, Share and Access Project DocumentsRFIs, Submittals, Transmittals

LOB – Ring Building CoordinationSlide18

LOB – Ring Building Coordination

Schedule Development Meeting Held 9/17/10EW Howell to Prepare & Submit Schedules:Preliminary 90 day: Due 10/4/10Detailed CPM Schedule: Due 10/25/10Schedule Development to Follow WBS FormatHowell using same scheduling consultant for both LOB & ISB projects

Schedule StatusSlide19

Conclusion

Successfully advanced LOB program by over 1 yearLOB Contractor has record of successful performance at BNLLOB & Ring Contractor site utilization requirements are establishedInitial interactions between the contractors are favorableHigh level of confidence in successfully completing LOBs with minimal impact on Ring Bldg