/
RISER PROJECT  n/o back to back kitchens RISER PROJECT  n/o back to back kitchens

RISER PROJECT n/o back to back kitchens - PowerPoint Presentation

phoebe-click
phoebe-click . @phoebe-click
Follow
345 views
Uploaded On 2019-06-29

RISER PROJECT n/o back to back kitchens - PPT Presentation

Why you are special Access to an n kitchen might be thru the o kitchen and vice versa Which one N or O The side that would be the easiestleast expensive to dismantle no backsplash old cabinetry etc ID: 760505

day kitchen sink continued kitchen day continued sink door water unit remove floor wall prepare general protection plumbers key

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "RISER PROJECT n/o back to back kitchens" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

RISER PROJECT

n/o back to back kitchens

Slide2

Why you are special!

Access to an “n” kitchen might be thru the “o” kitchen and vice versa!

Slide3

Which one? “N” or “O”?

The side that would be the easiest/least expensive to dismantle – no backsplash, old cabinetry, etc.

In case of a tie, “n” unit because tenting

isn

’ t as invasive.

Slide4

General information

When you see floor protection in the main hall from the service elevator to your unit you know we will probably be there the next day to start removing the wall.

floor Protection will be placed from your front door to your kitchen and will remain until your unit is complete

Monday thru Friday, Work will start at 8am. Since the sinks must be functional before the plumbers leave, it may continue until after 5pm.

Slide5

General information - continued

At the end of each day there will be water in the kitchen that did not have a wall removed

There will be a lot of noise

The service elevator will be used intermittently to bring in pipes, etc.

Slide6

General information - continued

When complete, the walls affected will be patched and prime painted

Cabinets , sinks and countertops will be re-installed

Ceiling to floor protection will be put up at kitchen (both sides in case of “N”) and will remain for the duration of the project

Slide7

The lay of the land

‘N” KITCHEN

“o” KITCHEN

Slide8

Wall opening for pipe exposure

Kitchen

Slide9

Now it gets ugly!

Slide10

Some positives…

Cleaner water

Hotter water

Better water pressure

Shut-off valves are under the sink

Slide11

Time line (using the term loosely)

The first day the contractor makes the hole in the wall – starting on the 19

th

floor.

The following day the plumbers start working

the plumbing and construction will take approximately 3-4 weeks

All dates and times are subject to change without notice

Slide12

How to prepare

Provide a copy of your unit key,

mark it clearly with unit number and Drop It in the office mail slot

If you do not have a duplicate key – have one made

All keys will be kept until after that riser is complete – you may not pick them up, at the end of each day

Keys will be kept in the management office

Remove any decorative key rings

Slide13

How to prepare - continued

Plumbers and contractors will be coming in and out of your units every day of the project

If you have pets - who want to bolt out the front door - put them behind a closed door or gate

Put a post-it note on your door telling the contractor that you have a pet or pets (how many?)

Slide14

How to prepare - continued

All of these ‘Housekeeping’ items should remain, in place for the duration of this kitchen riser.

if your kitchen is

not

being dismantled:

MAKE A CLEAR PATH FROM YOUR FRONT DOOR TO YOUR SINK

Remove everything around and under your sink

Empty your dishwasher

Slide15

How to prepare - continued

IF YOUR KITCHEN IS BEING DISMANTLED

REMOVE Everything from the cabinets above AND BELOW the sink

REMOVE EVERYTHING FROM YOUR “sink wall” COUNTERTOP

Remove everything from your dishwasher

Cover the furniture in the work area

Your kitchen will have limited access and there will be no running water for 7 to 10 days

Slide16

Slide17