Roadmap amp Milestones Production and installation in LS2 January Production start March Preproduction batch June End of production February End of modules tests August End of Tunnel Installation ID: 798752
Download The PPT/PDF document "SPS BPM system renovation" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
SPS BPM system renovation
Roadmap & Milestones
Slide2Production and installation in LS2
January
Production start
March
Pre-production batch
June
End of production
February
End of modules tests
August
End of
Tunnel Installation
February
End of HW
commissioning
April
End of commissioning
with Beam
2021
2020
2019
Slide3Production and installation in LS2
January
Production start
March
Pre-production batch
June
End of production
February
End of modules tests
August
End of
Tunnel Installation
February
End of HW
commissioning
April
End of commissioning
with Beam
2021
2020
2019
1 Technician/FSU
1 Expert 20% for debug
1 Technician/FSU
1 Expert x tunnel
1 Expert Surface
1 Expert
Slide4End of 2016 – 2017: issues and delays
November 2016: observed saturation with high intensity trains
Redesign of the analogue front end (see Manfred presentation)
February 2017: confirmation that the expected
r
adiation level is increased
Split of the GEFE in L-GEFE and C-GEFE
July 2017: crosstalk on the input LP filters of the BDF (ADC)Filters moved outside the board
Slide5Status in October 2017
VFC: contract being awarded. Production in 2018
[L-,C-]GEFE:
36 GEFE available for tests
L-GEFE
layout done. February 2018 first prototypesC-GEFE l
ayout done. February 2018 first prototypesBDF (ADC FMC): full production being assembledAnalogue Front-End (A-FE): see Manfred presentation
Slide6End 2017 – 2018: roadmap to LS2
October
A-FE Layout start
A-FE Layout review
and approval
2018
2017
2019
December
A-FE prototypes (10)
February
Installation of 2
A-FE and D-FE in BA4
March
End of Validation with
beam of the A-FE
May
Start of production
A-FE V2 (30)
June
Installation of as many systems as possible
September
End of qualification with Beam
November
Slide7End 2017 – 2018: roadmap to LS2
October
A-FE Layout start
A-FE Layout review
and approval
2018
2017
2019
December
A-FE prototypes (10)
February
Installation of 2
A-FE and D-FE in BA4
March
End of Validation with
beam of the A-FE
May
Start of production
A-FE V2 (30)
June
Installation of as many systems as possible
September
End of qualification with Beam
November
GW ready
End of Radiation Qualification
FESA SW available
FE automated test bench ready