1 21 st Century School Buildings Plan SCHOOL Bay Brook Building COMMUNITY MEETING Schematic Design January 31 2018 Introductions and Agenda Nicole Price Director Community amp Public Relations ID: 749401
Download Presentation The PPT/PDF document "Community Meeting: “Design Development..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Community Meeting: “Design Development” | Frederick | October 28, 2015 | www.baltimore21stcenturyschools.org
1
21
st
Century School Buildings Plan
SCHOOL
Bay Brook Building
COMMUNITY MEETING Schematic Design| January 31, 2018Slide2
Introductions and Agenda
Nicole Price
Director, Community & Public Relations
City Schools
Emily Sherman
Transition Support Coordinator
21
st Century School Buildings ProgramMichael Barry
21
st
Century School Buildings Program
Project Manager
Maryland Stadium AuthorityRick LeBlancArchitect Crabtree Rohrbaugh & Associates Architects
Introductions
Agenda
2
Overview & VisionPlanningDesignProject ScopeExisting Site AnalysisSchematic Site PlanSchematic Floor PlansBuilding Massing ModelProject Timeline
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide3
Overview
21
st Century School Buildings Program Update
The Baltimore City Public School System
(City Schools) Construction and
Revitalization Act of 2013 resulted in a
partnership between:
The State of Maryland
Baltimore City
City Schools
Each contribute $20 million
annually
towards the plan.
Current estimates suggest the funding
stream will support:
City Schools’ Plan is one of the largest public
works project in Baltimore City to date.
$977 million
in Phase I
23-28
school buildings
3
14K-17K
students
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide4
Overview & Vision
Investment in buildings, students
and communities
4
Overall school revitalization project has three goals:
to transform student opportunities and achievement;
(2) improve engagement and wellbeing of communities;
(3) help revitalize neighborhoods and communities. Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide5
6 Pre K
and Kindergarten Classrooms
2 Music Classrooms
6 Classrooms for Grades 1 and 2
1 Art Classroom
9 Classrooms for Grades 3, 4, and 5
1 Technology Lab10 Classrooms for Grades 6, 7, and 8Media Center
7
C
ollaborative Learning
Areas
Gymnasium4 Special Education ClassroomsCafeteria/Auditorium (Cafetorium)4 ES/MS Science Classrooms
Administrative, Health Suite
3 ESOL ClassroomsCommunity Space
5
Planning
Bay Brook Elementary / Middle School Proposed Classrooms and Spaces
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide6
6
Design Goals
Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
Strong Connection to the Community
Separate Parent and Bus Drop Off
Outdoor Play for each Grade Group
Promote Safety and Security thru Environmental Design
Sustainable Design – LEED Silver Certification
Daylight and Views for all Classroom and Learning Spaces
Building Orientation for Maximum EfficiencySlide7
7
Concepts Explored/Project Development
Design Concept
OPTION A
OPTION B
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide8
8
Concepts Explored/Project Development
Design Concept
OPTION C
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide9
9
Concepts Explored/Project Development
Design Concept
OPTION C
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide10
10
Garrison
Middle SchoolSite
Schematic Site Plan Site Organization:
▪ Provide for vehicular circulation from Virginia Ave with a parent drop off▪Orient the building to position the cafeteria and gym adjacent to the sports field and the recreation center.▪ Develop a pedestrian connection from the school to the recreation center.
▪ Retain main school entrance on Virginia Avenue with bus drop-off
Schematic DesignCommunity Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide11
11
Garrison
Middle SchoolSite
Schematic Site Sections
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSee handout #1Slide12
12
Garrison
Middle SchoolSite
Schematic Site Sections
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSee handout #1Slide13
13
Schematic Site Images
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
N
3
2
1
1
1
1
333
111
2See handout #2Slide14
14
Schematic Site Images
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
N
3
3
3
3
1
1
1
1
2
211
1122
See handout #3Slide15
15
Building Organization
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
N
Separate Public/Community Space from Academic Wing
Central Lobby Access
Central
Stair
Secure Academic Wing
Collaborative
Learning
Grade Groupings by FloorSlide16
16
Garrison
Middle SchoolSite
Proposed First Floor Plan
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide17
17
Garrison
Middle School
Site
Proposed Ground Floor Plan
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide18
18
Garrison
Middle SchoolSite
Proposed Second Floor Plan
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
NSlide19
19
VIEW LOOKING SOUTH EAST
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide20
20
VIEW LOOKING NORTH WEST
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide21
21
VIEW LOOKING SOUTH EAST
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide22
22
VIEW LOOKING NORTH EAST
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide23
23
VIEW LOOKING SOUTH EAST
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide24
24
VIEW LOOKING NORTH EAST
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide25
25
OUTDOOR SPACES
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide26
26
OUTDOOR SPACES
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide27
27
OUTDOOR SPACES
Schematic Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide28
28
COLLABORATION SPACE
COLLABORATION
CLASS
ROOM
LOCKERS
42” HIGH LOCKERS
CORRIDOR
Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide29
29
GYM SPACE
Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
Locker
Rooms
Access to outdoor play
Bleacher Area
Gym
StorageSlide30
30
CLASSROOM
Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide31
31
SCIENCE, MUSIC, or TECHNOLOGY LAB
Design
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.orgSlide32
32
Schedule
Schedule
Concept Design Meeting:
November 2017
Schematic
Design Meeting
:January 2018In School Design Review meeting
February
8, 2018
Relocation
and Transportation
MeetingFebruary 28, 2018Early Bid Packages:
March 2018
School Family Council Meetings- 21st
Century agenda item TBDMarch 21
st, April 25thMay 30
th
at 4:30 PM
Pre-construction Meeting
April/May 2018
Construction Documents:
May 2018
Bidding:
June 2018
Begin
Construction:
July 2018
Substantial Completion:
November
2019*
Community Meeting: Schematic Design | Bay Brook Building | January 31, 2018 |www.baltimore21stcenturyschools.org
*Date subject to changeSlide33
CONTACTS
Nicole Price
nprice@bcps.k12.md.us
Emily Shermanesherman@bcps.k12.md.us
21st Century School Buildings
Program Office(443) 642-4600
www.baltimore21stcenturyschools.org
Instagram @21stCSBaltimoreTwitter @21stCSBaltimore
Facebook
@21stCenturySchoolBuildingsProgram
Questions?
33Slide34
21st Century School Buildings Program
Baltimore City Public Schools
200 East North Avenue Room 407-B
Baltimore MD 21202
(443) 642-4600
Cheri Vincent
Interim
Executive Director, 21st Century Buildings ProgramBaltimore City Public SchoolsGary McGuiganSenior Vice President, Capital Development Division
Maryland Stadium Authority
Robert A.
Gorrell
Executive Director, Public School Construction Program
State of Marylandwww.baltimore21stcenturyschools.org
This presentation is brought to you by the
21st Century School Buildings Program
Thank You!