BHS 100 BUILDING REPLACEMENT BHS 100 BUILDING REPLACEMENT

BHS 100 BUILDING REPLACEMENT - PowerPoint Presentation

projoutr
projoutr . @projoutr
Follow
343 views
Uploaded On 2020-06-24

BHS 100 BUILDING REPLACEMENT - PPT Presentation

Board Meeting 053118 00 BISD Capital Projects BHS 100 Building Replacement Agenda Board Meeting 053118 BISD Capital Projects REVENUE 2015 Assumptions Bond 2016 ID: 785536

capital cost project 000 cost capital 000 project building bhs 100 total construction phase projects bond levy 2019 2018

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "BHS 100 BUILDING REPLACEMENT" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

BHS 100 BUILDING REPLACEMENT Board Meeting 05.31.18 00

BISD Capital Projects

Slide2

BHS 100 Building ReplacementAgendaBoard Meeting05.31.18BISD Capital ProjectsREVENUE

2015 Assumptions Bond 2016

2018 Project Costs

BHS 100 Building Replacement

Cost

Phasing

Work Plan Timeline

BHS 100 Building PHASE II

Finance

Next Steps

Questions

Slide3

REVENUE 2015 Assumptions Bond 2016 2018 Project Costs

00

BISD Capital Projects

Slide4

BHS 100 Building ReplacementWhy Don’t We Have Enough Money?2015 AssumptionsConservative request to taxpayersOptimize fund balancesTax stabilityMaximize interest earningsClass size reduction grantState Match eligibility (BHS) OSPI Calculation $2.6 (October 2015)Optimistic view of escalationDecember 2016 CoBI stormwater code revisionsBoard minutes October 29, 2015 “ Additional revenue sources include: OSPI State Match funds, Interest earnings, 2009 Balance”.

Board Meetng05.31.18

BISD Capital Projects

Slide5

BHS 100 Building ReplacementBond 2016ACTUAL BOND REQUEST 2016

+ PLUS

ASSUMED REVENUE 2015

State Match

$ 2,600,000

Class Size Reduction 1,200,000

2009 Interest Earnings 500,000

2016 Interest Earnings 500,000

2006 Blakely Fund Bal.

289,000

2009 Cap. Fund Bal. 5,420,854

TTL Assumed Resources $ 10,509,854

Blakely $ 39,000,000

BHS 100 Building 30,000,000

Essential Renovations 12,200,000

Total Bond Request $ 81,200,000

TOTAL ASSUMED

$ 91,709,854

Blakely

$

45,508,075

BHS 100 Building 33,866,341Essential Renovations 12,200,000

TOTAL ESTIMATES $ 91,574,416

Board Meeting05.31.18

BISD Capital Projects

ESTIMATES WITH ESCALATION 2015

Slide6

BHS 100 Building Replacement2018 Project CostsACTUAL BOND REQUEST 2016

State Match

$

2,600,000 TBD

Class Size Reduction

1,200,000

2009 Interest Earnings

500,000

2016 Interest Earnings

500,000

2006 Blakely Fund Bal.

289,000

2009 Cap. Fund Bal.

5,420,854*

2009 Cap. Fund (Blakely) 2,287,883

TTL Confirmed Revenue 3,576,883

TTL Revenue To Date $ 84,766,883

Blakely $ 39,000,000 BHS 100 Building 30,000,000Essential Renovations 12,200,000Total Bond Request $ 81,200,000

TOTAL DEFICIT $ 9,565,613

Blakely $ 47,161,518Deductive CO - 673,338Deduct CO Goal - 956,929Blakely 45,531,251BHS 100 Building 36,601,245Essential Renovations 12,200,000

TOTAL ESTIMATES

$

94,332,496

Board

Meeting

05.31.18

BISD Capital Projects

ACTUAL

WITH ESCALATION

2018/19

+ PLUS CONFIRMED REVENUE

2009 Essential Renovations Complete

*

District-wide

s

ecurity improvements, paint (Woodward, Sakai, Ordway), ILC improvements, BHS

Stadium

scoreboard|sound

, STEM classrooms, BHS breezeway replacement, HVAC, field storage,

water quality, storage improvements, photography retro-fit, BHS field equipment, district-wide

signage|striping

, portable

relocation|CoBI

stormwater

= $

3,132,971

Slide7

Provide Construction Cost (May 2018) $ 21,851,208

Escalation to May 2019 @ 5.88%

$ 1,284,851

Total Construction Cost May 2019

(Design/Bid/Build)

$ 23,136,059

Project Development/Soft Costs @ 48.2%

$ 11,151,580

Total Project Cost

$ 34,287,639

Bid Climate/Low

Competition -

10% on Construction Cost

$ 2,313,606

Total Project Cost

w/

Market

Premium

$ 36,601,245

Concept C* *Pre Final Ed Spec | CUP | ExclusionsProject Cost Estimate

Slide8

Provide Construction Cost (May 2018) $ 21,851,208

Escalation to May 2019 @ 5.88%

$ 1,284,851

Total Construction Cost May 2019

(Design/Bid/Build)

$ 23,136,059

Project Development/Soft Costs @ 48.2%

$ 11,151,580

Total Project Cost

$ 34,287,639

Bid Climate/Low

Competition -

10% on Construction Cost

$ 2,313,606

Total Project Cost

w/

Market

Premium

$ 36,601,245

Concept C* *Pre Final Ed Spec | CoBI | ExclusionsBond request April 2015 without escalation $30,000,000 ($6,601,245)Project Cost EstimateShortfall

Slide9

Provide Exclusions: Premiums for GCCM contracting. Allow 10% of Total Project Costs. Additional parking lots and site reconstruction beyond 2.5 acre siteCampus wide storm and water quality upgrades. Unforeseen conditions.Construction timeline and phasing

Construction

Cost

(May 2018)

$ 21,851,208

Escalation to May 2019 @

5.88%

$ 1,284,851

Total Construction Cost May 2019

(Design/Bid/Build)

$ 23,136,059

Project Development/Soft Costs @ 48.2%

$ 11,151,580

Total Project Cost

$ 34,287,639

Bid Climate/Low

Competition -

10% on Construction Cost

$ 2,313,606 Total Project Cost w/ Market Premium $ 36,601,245

Concept C* *Pre Final Ed Spec | CUP | Exclusions

($6,631,031)

($8M-$10M)

Project Cost Estimate

“Gap”

Slide10

BHS 100 BUILDING REPLACEMENT Cost Phasing Work Plan Timeline 00

BISD Capital Projects

Slide11

BHS 100 Building ReplacementProject PhasingBoard Meting05.31.18BISD Capital ProjectsMusic

DramaPERFORMANCE

EDUCATIONAL

PROGRAMS

PHASE ONE

PHASE TWO

Electives

CTE | Arts | SPED

THEATER

Slide12

Phase I

Phase II

© MAHLUM

Concept C :

Phasing

Slide13

CTE | ARTS | MUSIC | SPECIAL EDUCATIONBHS 100 Building ReplacementPhase I | IIBoard Meeting05.31.18BISD Capital Projects

PHASE ONEGraduation Requirement Emphasis400 student cohort

Fine Arts - 2 credits (4 semesters)CTE – 1 credit (2 semesters)

Current School Year 2017/18

1,787 Students enrolled in CTE and Arts Classes

213 Students

enrolled in

Music (excluding Vocal) Classes

108

Students enrolled in

Drama | Vocal Classes

PHASE TWO

Drama

Vocal

Slide14

Construction Cost (May 2018) $ 16,298,446

Escalation to May 2019 @ 5.88%

$ 958,349

Total Construction Cost May

2019

(Design/Bid/Build)

$

17,256,795

Project Development/Soft Costs @ 48.2%

$ 8,317,775

Total Project Cost

$

25,574,570

Bid Climate/Low

Competition -

10% on Construction Cost

$ 1,725,679

Total Project Cost

w/ Market Premium $ 27,300,249 $ 30,000,000

Concept C* 2016 Bond*Pre Final Ed Spec | CUP | ExclusionsCost Estimate:Phase I

Exclusions: Premiums for GCCM contracting. Allow 10% of Total Project Costs. Additional parking lots and site reconstruction beyond 2.5 acres. Campus wide storm and water quality upgrades. Unforeseen conditions. Construction timeline and phasing.

Slide15

Construction Cost (May 2018) $ 6,027,762

Escalation to May 2020 @ 10.6%

$

675,109

Total Construction Cost May

2020

(Design/Bid/Build)

$

6,702,871

Project Development/Soft Costs @ 48.2%

$

3,230,784

Total Project Cost

$

9,933,655

Bid Climate/Low

Competition -

10% on Construction Cost

$

670,287

Total Project Cost

w/

Market

Premium $ 10,603,942

Concept C*Exclusions: Premiums for GCCM contracting. Allow 10% of Total Project Costs. Additional parking lots and site reconstruction beyond 2.5 acres. Campus wide storm and water quality upgrades. Unforeseen conditions. Construction timeline and phasing. *Pre Final Ed Spec | CUP | ExclusionsCost Estimate:Phase II (1 Year)

Slide16

Supt. Advisory Work Group*Work Plan TimelineBoard Meeting5.31.18BISD Capital ProjectsSD | DD | CD | Building Permit w/approval for Phase I & Phase II (Alternate) Cost $36,601,245

2018

2019

2020

2021

May

June

July

Aug.

Sept.

Oct.

Nov

Dec.

Jan.

Feb.

Mar

April

May

June

July

Aug.

Sept.

Oct.Nov.Dec.Jan.Feb.MarAprilMayJune

JulyAug.Sept.Oct.Nov.Dec.Jan.Feb.MarAprilMayJuneApproval Phase I Concept CCapital Levy/Bond Resolution Nov 5 Election$36,601,245

$38,431,307Construction w/approval for Phase II $10,603,942 Escalation + $1,302,946Move in March 2021 **$40,352,873Construction Phase I - $27,300,249 Sept 2019 - Move in March 2021 Capital Levy/Bond Resolution Feb 12 ElectionCapital Levy/Bond ElectionCapital Levy/Bond Election

*Explore public and private options for additional funding and provide recommendations to school board.**These numbers assume a July 2020 Bid for Phase II separate from the bid for Phase I

Slide17

BHS 100 BUILDING PHASE II Finance Dave Trageser Managing Director Local

Government Finance D.A. Davidson & Co.

00

BISD Capital Projects

Slide18

BHS 100 Building ReplacementFinancing OptionsBoard Meeting05.31.18BISD Capital ProjectsVoted Unlimited Tax General Obligation (UTGO)BondsCapital Levy (Cash flow or Front-loaded with Non Voted Limited General Obligation (LGO) Bonds

Private Fund Raising

Stand-Alone Non-Voted Debt (LGO Bonds)

Repurpose Commons until future Master Plan funding is available

PHASE I

PHASE II

Bridging the Gap

Slide19

BHS 100 Building ReplacementDebt CapacityBoard Meeting05.31.18BISD Capital Projects

Slide20

BHS 100 Building ReplacementTax Rate PlanningBoard Meeting05.31.18BISD Capital Projects

$ 0.11

Slide21

Voted UTGO Bonds60% Yes vote required with validation requirementExcess levy to pay debt serviceAll proceeds available at closing20 years or longer fixed rate financing availableFor $8 million: Estimated $0.09/$1000 AV increaseAnnual tax increase $59 or $4.95 per monthFor $10 million: Estimated $0.11/$1000 AV increase

Annual tax increase $73 or $6.05 per month *Tax Base - Median Bainbridge Island Residential Assessed Valuation is

$

660,520 pursuant to Kitsap Assessor 2018 Levy Reports (DA Davidson).

BHS 100 Building Replacement

Financing Options

Board

Meeting

05.31.18

BISD Capital Projects

Slide22

Capital Levy50% Yes vote requiredLevy available annually to pay new construction and renovation costs1-6 year levyProceeds available based upon annual property tax collectionsNeed to be mindful of project inflation and tax collection percentagesMay “front fund” levy with Non-voted LGO Bond proceeds(Within 3/8 of 1% AV statutory authority equates to $27 million)BHS 100 Building ReplacementFinancing OptionsBoard Meeting

05.31.18BISD Capital Projects

Slide23

Capital Levy - continuedBond proceeds can’t pay for new construction, only renovationBond principal can be repaid from capital levy, but interest paid from other sources ie general fundFor $8 million project:6 year capital levy generates an approximate $0.17/$1000 AV increaseAnnual tax increase $112 or $9.36 per monthFor a $10 million project:6 year capital levy generates an approximate $0.21/$1000 AV increase Annual tax increase $138 or $11.56 per month

*Tax Base - Median Bainbridge Island Residential Assessed Valuation is $660,520 pursuant to Kitsap Assessor 2018 Levy Reports (DA Davidson).

BHS 100 Building Replacement

Financing Options

Board

Meeting

05.31.18

BISD Capital Projects

Slide24

Stand-Alone Non-Voted (LGO Bond)Issued with 3/8 of 1% statutory authorityPaid from general fund or other sourcesTake-out | pay-back or refinancing concernsBHS 100 Building ReplacementFinancing OptionsBoard Meeting

05.31.18BISD Capital Projects

Slide25

Private DonationsSteering Committee MembersCommunity InterestCorporate DonationsPartial FundingGrantsNaming RightsBOARD DECISION PHASE II TIME FRAMESNOVEMBER 2018 - FEBRUARY 18, 2019 ELECTION

JULY 2019 – NOVEMBER 5, 2019 ELECTION

BHS 100 Building Replacement

Financing Options

Board

Meeting

05.31.18

BISD Capital Projects

Slide26

Superintendent’s Advisory Work Group Board Approval for General Contractor | Construction Manager (GC/CM) – June 13Educational SpecificationsConditional Use Permit ProcessInterim Classroom LocationsFinal 2016 Bond Issuance

BHS 100 Building ReplacementNext StepsBoard Meeting

05.31.18

BISD Capital Projects

Slide27

QUESTIONSBoard Meeting05.31.18BISD Capital Projects