Olympia Headquarters Office Building Replacement Thursday September 28 2017 Application for DesignBuild Project Approval Introductions Scope Qualified Project Team Why Project is Suited for DesignBuild ID: 693036

design project september replacement project design replacement september olympia office building november 2017 wssda construction march 000 budget april completion 2018construction services

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Washington State School Directors’ Ass..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Washington State School Directors’ Association

Olympia Headquarters Office Building Replacement

Thursday, September 28, 2017

Application for Design-Build Project ApprovalSlide2

IntroductionsScopeQualified Project Team

Why Project is Suited for Design-BuildSchedule

Budget and FundingQuestions

Agenda

AgendaSlide3

WSSDA Olympia HQ Office Building Replacement

Scope

Existing SiteSlide4

Conceptual Plan

WSSDA Olympia HQ Office Building ReplacementSlide5

WSSDA Olympia HQ Office Building Replacement

Replacement of current 10,000 SF structure

Planned construction 7,500 SF on existing 2.14 acresConnect to sewer Energy efficient, technically up-to-date, durable

ScopeSlide6

Project TeamSlide7

Opportunity for greater innovation and efficienciesSignificant savings in project delivery time can be realized

Early Design and delivery of side sewerOffsite fabrication

Fast tracking design and construction

Exceeds Statute Requirements

Why Project is Suited for DB

Meets Two RCW 39.10.300 CriteriaSlide8

ScheduleDB Process September – November 2017

Project Review Committee Submit Application September 1, 2017Project Review Committee Presentation September 28, 2017

Advertise for Design-Build RFQ September 29-October 12, 2017Statement of Qualifications Due October 30, 2017Short-list and send RFP November 3, 2017Interview and Fee Proposals November 13-21, 2017Select Design-Builder and Award November 22, 2017Schematic Design November 2017 – January 2018

Design Development January – March 2018Construction Documents March – April 2018Permitting March – May 2018Construction June 2018 – April 2019Substantial Completion April 2019Final Completion/Closeout July 2019

ScheduleSlide9

WSSDA Olympia

HQ Office Building Replacement

Estimated project design and construction (including construction contingencies)$1,700,000Costs for Professional

Services (PM/CM Services, Legal)$100,000Equipment and furnishing costs$113,000Project Contingencies (8%)$134,000Other related project Costs (Utilities, Testing/Reports, Permits, Consumables, Moving, etc.)$379,000Sales Tax$200,000

Total Budget

$2,626,000

BudgetSlide10

Centralia High School ModernizationQuestions?