H Rauer DLR PF H KinterA Salado KayserThrede 2 Activities Mission selection in Feb 2014 Payload industrial management is being assigned for bridging period and B1 Phase to ID: 795523
Download The PPT/PDF document "PLATO PLATO TOU KO MEETING" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
PLATO
PLATO
TOU KO MEETING
H.
Rauer
(DLR PF)
H. Kinter/A. Salado
(Kayser-Threde)
Slide22Activities
Mission selection in Feb. 2014
Payload
industrial management is being assigned for “bridging period” and B1 Phase to
Kayser-Threde
Status
of
payload
teams
, PDC, PSPM
is
reviewed
„Kick-off“ Phase B1:
July
16/17
Slide33Activities since
selectionConsortium
:
Consortium
working
groups
have
(
re
-)
formed
:
CCD
working
group
(
chair
D. Walton)
Data
P
rocessing
Algorithms
Working
Group
(
chair
: R. Samadi)
Telescope
Optical Unit Working Group
(
chair
: R. Ragazzoni)
Slide4Data processing group4
A Data Processing Algorithms Working Group has
been
re-initiated
PLATO-ALGO
(
chair
: Réza Samadi):
in charge of the study and the definition of the on-board and on-ground data processing algorithms (L0/L1)
provide specifications for the development of the on-board and on-ground
softwares
The group includes members of the
payload,
PDC
and PSPM teams
Slide5Telescope Optical Unit group
5TOU team (
chair
:
Roberto Ragazzoni):
First meeting in B1 phase is
scheduled on June 11 in Catania
update
on the
status
plan
the next study phases.
Slide6Upcoming meetings6
1st
P/L Meeting
has
been
May 06/07, 2014 @ DLR, Berlin
Consortium
kick-off
meeting
on
July
16/17, 2014,
@ DLR,
Berlin
PDC
meeting
July
15, Berlin
TOU
meeting
June 11, Catania,
Italy
2
nd
P/L Meeting proposed Fall
2014
Workshop on planet
formation
, Sept., London
PLATO 2.0 Science Workshop
December
2014,
Italy
Slide77
Slide8PLATO Camera Management Support Overview
Slide9KT Team Organization and responsibilitiesMain Phase B1 Preparation
ActivitiesB1 Schedule Overview: KT Questions to TOU teamAgenda
Slide10PLATO Payload Consortium
Slide11PLATO Payload Management Key Personnel
Name
Function
Richard Haarmann
PIPM
Bernd Schulz
PA/QA Manager
Alejandro Salado
Payload
Sys. Engineering (PTC)
Hilda Kinter
Camera Project Manager (
CPM)
PIPM
Deputy
Valery Mogulsky
Camera Systems
Engineering
Roberto Montedori
Payload AIV Manager
(
PAM)
Gisbert
Peter
DPS Project Manager (DLR)
Slide12Camera Management at Kayser-Threde:Key Personnel roles and responsibilities definedSupport the TOU in the preparation of phase B1
Interface to Camera consortium membersTechnical and managerial contact pointsMain Phase B1 Preparation Activities
Slide13Phase B1 PlanningDetail roadmap until KO Phase B1 and beyondSynchronization of all partner activities
Major Milestones for the Phase B1Main Phase B1 Preparation Activities
Date
Event
15.-16. July 2014
Phase B1 Kick-Off
March 2015
PLATO Design Consolidation Review (PDCR)
October 2015
PLATO
B1
data package
delivery for
SRR
November - December 2015
PLATO System
Requirements Review (SRR)
March 2016
Mission Adoption & IPC approval
April 2016
Kick-off Phase B2/C/D
January 2024
PLATO Launch
Slide14Preparation B1 Kick-Off Data PackageMain Phase B1 Preparation Activities
Establish an updated Specification Tree to define the interrelation between the single PLATO P/L
component specifications
Basis for the traceability of single requirements and interface management
Definition of all required documents
for the B1 Kick-Off
Comparison with existing documentation to identify necessary inputs
Completion /
annotation of existing specifications
Utilization as applicable documents for the B1 work upon PDCR
Slide151st P/L Meeting has been on 06./07.05.2014Bring P/L consortium togetherStart to resume P/L teamsPhase B1 KO is scheduled for 16./17.07.2014Official Start of Phase B1
All work packages are already definedTasks to be done between KO and 2nd P/L Consortium Meeting will be defined2nd P/L Meeting proposed Fall 2014All specifications and belonging annotations/supplements are available as basis for the B1 development workPhase B1
Slide16PLATO Phase B1 Schedule
Slide17Overview of major Phase B1 Deliverables
MeetingDateDeliverablesKO16.07.14
* Drafts of
TOU Requirements
Specification,
Camera
Development
& Verification Plan,
List of
Deliverables,
2nd P/L Meeting
15.09.14
* First
issue of above documents
PM1
18.11.14
Progress report + specified deliverables
PM2
20.01.15
Progress report + specified deliverables
PDCR delivery
02.03.15
Progress report + specified deliverables
PM3
12.05.15
Progress report + specified deliverables
PM4
21.07.15
Progress report + specified deliverables
PM5
22.09.15
Progress report + specified deliverables
SRR delivery
02.11.15
Camera
Reports, models, Camera URDs and I/F documents
*
drafts to be prepared
by KT
Specified deliverables defined in the List of
Deliverables, which may include
Camera Reports (design, budgets, performance,
straylight
, thermal, structural, risk assessment), MAIV plan, Management Plan, mathematical
models
Slide18Communication between TOU team and KT
List of all deliverables to be defined and finalised by 2nd P/L Meeting PMs to be held at TOU site or by
Webex
. Required documents and Progress Reports including status of AIs to be delivered at least five working days before the meeting
Regular bi-weekly
telecons
between TOU
lead team
and KT:
brief discussion of working progress, identified problems, needed inputs
etc
the traceability of single requirements and interface management
Meeting when necessary with other
Camera/Payload/PLATO
teams by
Webex
(organised by KT). For critical topics, like I/F discussions, face to face meeting are preferable
Slide19Goals Phase B1: To achieve a sufficient level of technical maturity to ensure a successful SRR.
system requirements for the selected architectures successfully validated system
requirements
derived
confidence
on the readiness levels of various technologies.
Payload Camera Subsystem Status Summary:
Goals Phase B1
consolidating
the
requirements
on system and subsystem level and their
traceability
consolidating
internal interfaces
, assessing requirements for
external
interfaces
consolidating
performance
models
consolidating
and defining
operational modes
of the payload and its various subsystems and components
.
validating
the set of
system and subsystem requirements
Establish a
verification strategy
consistent with programmatic limitations and required scientific value.
Develop
technology maturation programs
in order to achieve the required TRL levels at SRR
Slide20Team?Several Institutions (INAF, Univ. Bern, Stockolm Obs., Univ. Firenze) + Industrial Partners (Selex ,
Medialario-Sagem, Seso, RUAG, APCO Technologies) led by INAF (Interface to Camera team)Current Status?Optical Design + options availableBreadboard/Prototypes: TOU AIV procedure already performed
(
TOU Optical and Thermal
Performance)
Further Breadboard
with AIV and thermal behavior
identified
AIV
procedures
under development with
serial production in
mind
Next Steps
?
Answer
MEMO questions
Telescope
Optical Unit (TOU
)
Status Summary:
Slide21Issues/questions to the TOU Team
Slide22Questions to/inputs from TOU team:List of TOU team including percentage allocation for PLATOIs there a Central point for Camera document collection?
List of available technical documents: List of MEMO QuestionsComponent I/FsOperational modes, states, and transitionsPerformance models or simulatorsBehavioural models or simulators
Performance
wrt
requirements
Model philosophy
Assumptions employed in analyses
Requirement specification
Open issues and decisions
Current risks and their mitigation strategies
Main Phase B1 Preparation Activities